1.
Call to Order.
10:10 a.m.
2.
Roll.
Directors
Amoroso and Comstock; General Manager Jennifer Blackman also present.
3.
Draft Update of Five-Year Capital Improvement Plan.
Staff
presented an updated version of the district’s Five-Year Capital Improvement
Plan (“CIP”) for 2016-2021 and staff’s priorities for the 2016-17 fiscal
year. First, on the water side of operations,
the sliplining of the overflow pipe from Woodrat #1 (at an estimated cost of
$75,000) has been identified as a project to complete this year if possible to
preserve the integrity of this piece of infrastructure. Discussion ensued about the amount of lead
time needed for this project, given potential engineering/design time and given
that the work can only be done when the reservoir itself is low enough (i.e,
the water level in the reservoir is low enough) to do the work. Director Comstock suggested that a flow-chart
of the various capital projects might be helpful, in order to factor in
engineering, design, planning and administrative time in addition to the actual
construction/installation window. Staff
next noted that the next phase of the chlorine disinfection byproduct project also
is included in the CIP’s 2016-17 fiscal year ($50,000) – specifically, funds are allocated for the
installation of the coagulation process, assuming this is approved by the Board
and the district’s regulators at the State Water Resources Control Board
(“SWRCB”). In addition, the rehabilitation of the East
Tank, one of the district’s two treated water storage tanks, is on schedule for
the 2016-17 fiscal year. This is an
expensive project, but it is necessary based on an inspection of the tank and
an assessment by staff of overall priorities; adding this project to the
upcoming fiscal year will have a significant impact on the budget process given
the $160,000 estimated project cost. Finally, in light of the planned projects
described above, staff has retained the “Tier 2” distribution pipeline
replacement projects on the CIP, but has moved each “forward” a year as it is
unlikely the district will be able to install any of the pipeline projects
during the upcoming fiscal year.
Second,
on the wastewater side of operations, staff noted that the wetwell
rehabilitation project is now scheduled for installation during the 2016-17 fiscal
year (installation has been deferred pending completion of the lift station
pump replacement project); funds for the wetwell rehabilitation project were
budgeted and collected during the 2015-16 fiscal year. Staff also has prioritized the replacement of
the perimeter fencing behind the properties located on Overlook Road and plans
to do this project in-house. Discussion
ensued about the types of projects staff can complete in-house vs. those that
need to be contracted out; staff explained that it is much more difficult for
the crew to undertake projects requiring heavy equipment expertise or projects
requiring an uninterrupted dedication of time (such as two weeks to install a
section of pipeline, for example) because of the demands of daily
operations. Staff is best positioned to
do smaller projects, such as hydrant replacement, meter upgrades, or building
upgrades, that can be done in stages and without the need to rent heavy
equipment or contract-out for specialized equipement operators.
Director
Comstock said he understands why the projects have been prioritized as they
have and he agrees with staff’s prioritizations, but he is concerned about
pushing back the pipeline replacement projects too far given the amount of
pipeline that has been identified for replacement. Staff
noted that the projects as identified have been added to the expense side of
the budget and resulted in a $200,000 deficit that will need to be funded, so
it doesn’t seem possible to include pipeline replacement at this time. Director Comstock said the challenge for the
district is its obligation – with a small staff and small customer base -- to maintain a large amount of infrastructure,
which will not get any less expensive to do over time. Staff
noted that the draft CIP contemplates the installation of nearly $300,000 worth
of Tier 1 capital improvement projects, which is a significant increase over
what has been done historically. Each
one of these projects require a tremendous amount of energy to plan, design and
implement, and staff does not want to spread the district too thin across too
many projects in one year – even if a pipeline project is contracted out, for
example, it requires staff to plan and oversee the design, implement the bid
process, and supervise the installation.
Discussion
turned to some of the projects planned for several years out, including the
upgrade of the irrigation pump station and aeration process at the sewer
ponds. Per the Board’s direction, staff
has been working with Oswald Green Technologies and Allied Engineers on a
“master plan” for this work and staff anticipates a comprehensive
recommendation will be completed within the next few months. With regard to other projects, staff is
planning to complete the purchase of a new utility truck during the present fiscal
year and has scheduled funds for an assessment and possible design of a new
septic system for the office building.
4. Draft Fiscal Year 2016-17 Budget.
Staff said that in this revised
version of the draft budget, no changes have been made to the operations
section of the budget. Staff noted that
a 3% wage increase is assumed based on the Bay Area CPI, but staff has not yet had
time to meet or present a specific request to the Personnel Committee. Staff
directed the Committee’s attention to page 6 of the draft budget, which
reflects the $305,000 anticipated capital improvement costs; staff also has
reduced the amount of budgeted revenue anticipated from water sales from
$100,000 to $90,000. As a consequence,
there is a $212,000 “gap” between proposed expenditures and proposed revenues –
however, there is no rate increase yet budgeted, nor has staff proposed a
reduction in funds to be deposited into reserves (neither of which is realistic
given the planned expenditures).
Discussion ensued about the status of reserves and staff promised to
update the reserve spreadsheet for the next meeting. Director Comstock requested that staff also
re-circulate a copy of the Financial Reserve policy adopted by the Board last year. He noted that sewer reserves quite likely
will fall below “0” as a consequence of paying for the lift station pump
replacement project. Staff agreed and
said the district’s customers likely are expecting a rate increase to pay for
that project; in the next version of the
budget, staff will propose a service charge increase for both water and sewer
to “close the gap” between revenues and expenditures. Director Comstock said it seems that at least
a 10% increase in both water and sewer service charges, as well as borrowing
from reserves, will be required.
5.
Community Expression
None.
6.
Adjournment
11:55 a.m.