MINUTES
1.
Call to Order.
7:33 p.m.
2.
Roll.
Directors
Amoroso, Comstock, Siedman and Smith present; director Siedman presiding. Director Siedman noted that director Godino is
attending the meeting by telephone.
3. Manager’s Report.
-- Update
on the Terrace Avenue Bluff Stabilization Project.
Staff reported that the County of Marin held a
hearing on August 13, 2015 before a Deputy Zoning Administrator on its
application for a coastal permit to install the road-level retaining wall project
at Surfer’s Overlook. The Board was
referred to the County staff report, which recommends approval of the permit with
conditions. As described in the staff
report, the County plans to replace the three existing but deteriorated retaining
walls with one single continuous wall that will span approximately 340 feet. The replacement retaining wall will be aligned
so that it is entirely within the Terrace Avenue public right-of-way.
Staff
noted that the County of Marin plans to send a letter about the project,
including an outline of the steps required for the transfer of funds raised to
pay for the project, to the Bolinas Community Center, which is the fiscal
sponsor for the local fundraising committee.
The letter will be sent next week, with comments due on September 8th. The Board of Supervisors likely will
authorize the project to be advertised for bids at its regular meeting on September
15th.
Importantly,
the County of Marin likely will close Terrace Avenue at Surfer’s Overlook to vehicular
traffic for the duration of the project.
This is necessary in order to expedite the installation of the project
which will be performed between October 15th – December 15th. Vehicular access will be blocked 24/7,
whereas pedestrian traffic will be allowed except when there are safety issues
posed during certain phases of the project.
-- Update on the BCPUD Chlorine Disinfection
Byproduct Reduction Project.
Staff
directed the Board’s attention to a report by Lewie Likover concerning the
district’s coagulation pilot project.
The first step in this pilot project was performed in mid-July and test
results show that coagulation prior to filtration reduced TOCs and dissolved
carbon (both of which are DBP precursors) by over 50%. The district has since installed a new dosing
pump with a calibration column. Lewie
has bucket-tested water from the reservoir that has been run through the
coagulation pilot and membrane filters for TTHMs and HAA5s. Thus far, he is seeing a reduction in color,
which is a good sign. If the test results
for this water are promising, the next phase will be to run water from the
Arroyo Hondo water source through the coagulation pilot project.
--
Proposal by Conservation Corps North Bay to Remove Invasive Vegetation Adjacent
to Solar Arrays at 101 Mesa Road and 400 Mesa Road.
Staff presented a proposal to the district
solicited from the Conservation Corps North Bay (“CCNB”) for removal of
encroaching vegetation around and under the photovoltaic arrays at the sewer
pond and water treatment plant sites.
The cost proposed is just under $5,000 per site for CCNB crews to work
two full days at each site. Staff has
solicited a proposal from another company to compare with the CCNB
proposal. If, as expected, the CCNB
proposal is the lowest, staff would like to proceed with the vegetation removal
at the water treatment plant site as the encroaching poison oak and other
plants there are quite extensive.
Staff reported that water consumption in the
district increased somewhat during the most recent quarter on the Mid-Mesa
(May, June, July). However, when the
first seven months of the year are compared with the first seven months of last
year, consumption thus far in 2015 is virtually identical to consumption in
2014. The district continues to supply
the town with drinking water exclusively from the Arroyo Hondo water source,
but it likely cannot continue to do so if the warm weather continues. Consumption has been spiking up over the
weekends when coastal visitors are in town and creek levels also drop when the
temperature rises. Staff continues to monitor
supply and demand closely; creek levels come back up when the weather cools and
when demand drops back down during the weekdays. Staff said the district probably will need to
access its emergency reservoir water during the Fall months.
The new air compressor ordered by the
maintenance crew arrived today and will be installed at the treatment plant
soon. The district experienced a small
leak on Grove Road (between Alder and Elm), which was detected and repaired
yesterday. Staff noted that the
district’s part-time laborer, Ryan Fitzgerald, has been a tremendous asset as
he has been able to assist with many projects, including vegetation management
and mowing, water meter replacement, maintenance yard organization, back-hoe
operations, etc.
Staff directed the Board’s attention to the
binders, which contain copies of a power point presentation delivered by staff
at the Association of California Water Agencies (“ACWA”) Marin Water Forum on
July 24, 2015. In this presentation,
staff described the district’s water sources, as well as its water treatment,
water storage and water conservation efforts.
Staff noted that one of the most interesting presentations by Humboldt
County area water managers about the impact of illegal marijuana cultivation on
water quality and quantity in that area.
Staff presented a revised version of the
proposed amendment to the district’s Franchise Agreement for solid waste
disposal services with Redwood Empire, Inc. and inquired if the Board is now
ready to proceed with the Proposition 218 notification and public hearing process. Staff noted that the amendment: (1) extends the
term of the franchise agreement from 2015 to 2030 and (2) establishes new rates
for the term of the agreement. The
amendment also includes provisions requiring
the company to make certain quarterly reports to the district, pay the district
a $5,000 annual franchise fee, and affirm its commitment to maximizing the recycling
of recyclable materials. Director
Comstock requested that the amendment be clarified to state that the company’s
quarterly reports will be specific to waste from Bolinas (and not Countywide)
and staff agreed to raise this point with the company.
On the wastewater side of operations, staff
reported that the flows remain low into
the collection system. Staff is finishing
up spray season and performing end-of-season mowing in and around the spray
fields. Bailey Greene from Oswald Green
Technologies is planning to visit the district this Friday as part of his
ongoing efforts to draft a “master” proposal for certain improvements to the
wastewater treatement process at the ponds.
The Board reviewed correspondence sent and
received since the last regular meeting, including an update from the County of
Marin on its Climate Action Plan and the district’s receipt of a second Zero
Waste Grant of $3,500.
--
Drainage Project Manager’s Report.
The Board received a drainage report from
Lewie Likover.
4.
Community Expression.
Director Siedman noted that
the Board’s binders contain an anonymous letter dated July 16, 2015 concerning
extensive construction on a lot near Elm Road between Grove and Hawthorne Roads.
Director Amoroso said that several
people have approached him about this construction and he has directed them to
the County of Marin, which has jurisdiction over land use and building in the
unincorporated areas of the county, such as Bolinas.
5.
Request for Financial Relief from Quarterly Water Bill
pursuant to BCPUD Resolution 553 – 75 Wharf Road, Bolinas (J. Hartley)
Director
Siedman observed that Jane Hartley is present and said the Board has copies of
her letter from May 2015 concerning a leak under her house at 75 Wharf Road. He notes that the BCPUD turned off the water,
notified her of the leak; she came out the next day, hired a plumber and
replaced the water line to the house.
Director Smith asked how long the leak had been going before she was
notified. Ms. Hartley said it probably
leaked for about three weeks before she was notified. He said that although she would have seen
the leak sooner if she was home, she did address it immediately upon being
notified by the district of the problem, so it is consistent with the Board’s
past practice to forgive the amount of the bill attributable to the leak. He noted, however, that all Bolinas
homeowners who do not live full-time at their property should invest in a house
valve and turn the water to their homes off when they are not there so that
this kind of water loss does not occur.
V. Amoroso/L. Comstock all in favor to forgive the amount of the water bill attributable to the leak,
based on the historic three-year average water use during the same quarter.
6.
Request to Remove Dead Pine Tree in 400 Block of
Hawthorne Right-of-Way, between Larch and Poplar Roads. (C. Duchamp)
Director
Siedman noted that district staff has confirmed that the tree in question is
dead and is located in the public right-of-way, which is a “paper” right-of-way
at this location and not developed as a road.
Given that the tree is clearly dead, staff believes it is not necessary
to require Ms. Duchamp to pay for an arborist report. Ms. Duchamp has received a proposal of $1200 to
remove the tree, which she says threatens a nearby fence, and she and her
neighbor Colleen Hicks have agreed to contribute $200.
Discussion
ensued between the Board members about the propriety of the district paying for
the removal of a tree that is not located adjacent to a developed road and
which does not jeapordize the district’s water lines. Director Siedman noted the district is
expecting to receive another request to remove hazardous trees from the Dogwood
right-of-way which are overhanging a developed road and adjacent to homes (an
arbortist report has been submitted concerning the hazards posed by these
trees). The Board ultimately decided to
defer the request pending more information about the likely costs involved to
address the hazards posed by the trees in the Dogwood right-of-way.
7. Osterweis
Design Review, 200 Pine Gulch Road, APN 188-140-11, Project ID: 2015-0228 (to
construct a new swimming pool on a
developed lot in Bolinas).
There was no public comment on this agenda
item.
8.
Sewer Pump Replacement for the Wharf Road
Lift Station: Lift Station Pump Replacement Report by West Yost Associates.
Staff reported that the district engaged West
Yost Associates to evaluate the failure of the district’s pumps at the Wharf
Road lift station and recommend replacement pumps. The engineers considered the following
factors: the replacement pumps should
(1) match the existing pump capacity of 220 gallons per minute; (2) achieve a
total dynamic head requirement of 232 feet (209 of static lift and 23 feet of
pipe friction losses); (3) have a minimum pump efficiency of approximately 57
percent; (4) require not more than 30 HP given the existing electrical capacity
at the station; (5) be able to handle typical municipal wastewater with or
without grinders; (6) demonstrate a high degree of reliability; (7) operate at
motor speeds of 1,800 RPM or less; (8) have components that are easily
accessible for maintenance by district staff; (9) be capable of installation in
the existing pump room with minimal modifications; and (10) be deliverable as
soon as possible.
The engineers analyzed non-clog centrifugal
pumps, centifugal chopper pumps, and positive displacement rotary lobe and progressive
cavity pumps made by several different manufacturers. Many of the pumps were not feasible for the
district’s application due to the specifics of the performance needs. A pump manufactured by Flygt is a feasible
alternative, but would require an upgrade of the electrical service at the lift
station and would have to be run at higher-than-optimal RPMs of 3600. After evaluating all alternatives, West Yost
recommends that the distict purchase the Vogelsang two-stage marathon pump,
which meets the districts requirements and has several installation and
operational advantages over the Flygt pumps.
West Yost also provided an installation drawing demonstrating how the
pumps should be located in the pump room.
Director Siedman urged the Board to move
forward with the purchase of the pumps as recommended by West Yost.
L. Comstock/G. Godino all in favor to
accept the recommendation of West Yost Associates and authorize staff to
purchase two of the Vogelsang two-stage marathon pumps for installation at the
Wharf Road lift station as soon as possible.
Directors Smith and Amoroso both stated that
they feel the district should schedule an inspection of its force main either
coincident with the installation of the new pumps (if possible), or after the
new pumps are in place. Director Smith
also suggested that staff confirm the dimensions of the pump room as the
drawings relied upon by West Yost are “as built” drawings and may not be exact;
staff agreed to do so.
9.
Marin Local Agency Formation Commission: Countywide
Water Service Study (Municipal Service Review – Draft Report, August 2015).
Staff reported that Marin LAFCO has issued a
300-page Countywide Water Service Study report in draft form. The draft report was released just days prior
to the agency’s August 13th meeting, which staff attended in order
to provide initial comments. Staff
therefore only had time to review the first 100 pages of the draft report,
which is an executive summary and overview.
Marin LAFCO plans to hold a public hearing on September 10th
to open up a 60-day public review process.
Staff commended the report overall, which represents a tremendous amount
of work by Marin LAFCO staff, but there are important errors in the report as
it pertains to the BCPUD and these errors need to be corrected.
Staff therefore attended the August 13th
Marin LAFCO meeting to highlight the district’s concern before the public review period opens. Staff told the commissioners that the BCPUD
works hard to conduct education and outreach with its customers and provide
them with accurate and timely information about their water system; the
district takes its responsibility to provide safe drinking water and
sustainably manage its resources very seriously. The BCPUD values its relationship of
confidence and trust with its customers and maintaining that trust is a matter of
personal and professional integrity for the Board and staff. Staff told the commissioners that BCPUD’s
customers need to know they can trust the district to give them accurate
information and this is why it is so important that LAFCO gets the facts right
in this report. Unfortunately, there are
at least two main points in the report that are not correct: (1) the report asserts that “usage” for most public
water systems (including the BCPUD) has been “intensifying” and (2) that
BCPUD’s treatment capacity is not sufficient to meet current and future
demand.
The first point,
that water usage is intensifying in Bolinas, is demonstrably false; in fact,
water usage in the district over the past nine years has decreased by an
average of 4.6%; staff provided LAFCO with this data but LAFCO has chosen not
to include it (at least thus far) in its report. The second point, that BCPUD needs to
increase its treatment capacity at the Woodrat Water Treatment Plant similarly
is misguided and based on a misunderstanding of “peak day demand”
statistics. In fact, the BCPUD’s water
plant operates at approximately 50 – 60% of capacity, on average, throughout
the year. As staff said to the the LAFCO
commissioners, it would be irresponsible for BCPUD staff to recommend diverting
scarce revenue dollars to expand its treatment capacity under the
circumstances.
Finally, the draft
report describes Bolinas as having “older and poorer residents” as compared to
past years and suggests this will pose “increasing challenges” for “funding
water operations and improvements in the long run.” Staff told the commissioners that the
district’s observations are the opposite – that real estate costs are soaring
and a much younger and wealthier demographic is moving into town. However, the BCPUD does not have access to
the sort of demographic or income data to specifically refute Marin LAFCO’s
conclusions.
Director Siedman said that Marin LAFCO seems
to be going beyond its jurisdictional mandate to be making recommendations
about how the district should operate it’s treatment plant, among other things,
and he queried what Marin LAFCO actually is empowered to do and what the
BCPUD’s responsibilities are in responding to the report. Staff said that the authorizing LAFCO
legislation focuses on sphere of influence and municipal service reviews, so the
subject report is within its scope.
However, it is important that the ultimate report is accurate and, at
the very least, that the BCPUD submit comprehensive written comments
Staff requested that at least two BCPUD
directors attend the September 10th hearing with staff to underscore
the district’s concern about the report.
Director Godino expressed frustration that Marin LAFCO has not made the
changes recommended by the BCPUD to correct inaccuracies despite multiple requests. Staff said the other water districts have
similar frustrations and the district managers plan to meet again to discuss a
coordinated strategy. Staff noted that
much of the districts’ input has made it into the report, but the report is
such a massive undertaking that LAFCO staff probably has been challenged to
manage all of the information provided by the various districts.
10. BCPUD
Resolution 639: Cites Board of
Directors’ Choices for Determining Fiscal Year 2015-16 Appropriations Limits.
Staff explained that the state constitution limits
the amount of revenue which can be spent/appropriated by all entities of
government, based on the 1978-79 base year of revenues (Gann Initiative). The appropriation limits apply to tax revenue
(allocated to the BCPUD by the County of Marin) and the constitution requires
an annual review of limit calculations, based on growth of population and
inflation. Staff has conducted the
review and calculated the district’s appropriations limits for the upcoming
fiscal year (which is the subject of the next resolution).
V. Amoroso/L. Comstock all in favor to
approve BCPUD Resolution 639, which cites the Board of Directors’ choices for
determining FY 2015-16 appropriations limits.
11. BCPUD
Resolution 640: States District’s
Appropriation Limits for Fiscal Year 2015-16.
L. Comstock/D. Smith all in favor to
approve BCPUD Resolution 640, stating the district’s appropriation limit for FY
2015-16.
12. Update
on Proposed Sale of College of Marin Properties in Bolinas.
Director Siedman reported that the word on
the “grapevine” is that the College of Marin is reconsidering selling its
Bolinas properties at all. He said that
there was supposed to be an RFP for proposals to purchase the properties, but
it is been “back burnered”. He has
attempted to find out more about this, but has been unable to get any specific
information. Director Siedman suggested
that the district write to the College of Marin and request to be notified
(i.e., provided any agenda) when and if the trustees are scheduled to discuss
the Bolinas properties. Staff agreed to
do so.
13. Water
Supply Update.
This item was deferred to the September
meeting as the district’s consulting hydrogeologist is on vacation.
14. Volunteer
Committee Reports.
--
Bolinas Lagoon Advisory Committee: Nothing to report.
-- Downtown Parking &
Traffic Committee: Nothing to report.
--
Resource Recovery: Purchase
of Erosion Control Materials.
Staff
reported that Jeff Creque has recommended specific improvements to the compost
berm that was constructed adjacement to the drainage ditch behind the Resource
Recovery Project site to repair a small hole and prepare the site for the rainy
season. The cost is expected to be
approximately $1,000, which should be shared between the four participating
districts. The Board had no objection.
Staff
further reported that the State Water Resources Control Board (“SWRCB”)
recently issued an order applicable to composting operations in the state. The SWRCB contacted the district and asked if
it intends to apply for coverage under the new rule for the RRP site. In consultation with Jeff Creque, staff
responded that the district does not intend to apply for coverage as it
believes it is exempt.
--
West Marin Mosquito Control Coordinating Council: Director
Amoroso stated that the council has a meeting scheduled in the near future to
discuss the Marin/Sonoma Mosquito & Vector Control District’s possible
interest in using mosquito and vector control substances the council has
opposed in the past. A reporter from the
Point Reyes Light said the Marin/Sonoma Mosquito & Vector Control District
has issued a programmatic EIR for its integrated vector management program. He noted that a number of different chemicals
are mentioned in the document.
--
Land Stewardship Committee: Director Siedman reported that the Committee
will next meet on August 28th.
15. Other
Business.
a. Board Committee Reports.
-- Finance:
Director Comstock noted that the
replacement of the lift station pumps is not a budgeted item so the funds to
pay for the pumps will need to come from the district’s reserves. Director Amoroso agreed and said the Board
will need to evaluate whether/how to replenish the reserves expended. Director Siedman said the Finance Committee should
make a recommendation in connection with the next budget process. Staff said the field audit for the district’s
annual report has been scheduled for September 23rd, so she
requested that any committee meeting take place after that date.
-- Legal: Nothing to report.
-- Mesa Septic, Flood Control and Roads: Nothing
to report.
-- Operations: Nothing
to report.
-- Park and Recreation: Director Amoroso reported that he attended the
most recent Mesa Park board meeting.
Apparently on a recent Sunday an ultimate frisbee group from San
Francisco arrived to use the field at the same time as the local soccer
group. The groups subsequently
negotiated a usage agreement whereby the Frisbee group will use the field on
Saturday and the soccer group will continue its Sunday use of the field.
-- Personnel: Update on Hiring Process for Full-Time Shift
Operator. Staff reported that the
district received 32 applications and staff has identified a slate of five
candidates for the Personnel Committee and staff to review. The Committee agreed to conduct the interviews
during the week of August 31st.
Staff said September 1st, 2nd or 3rd would be the best days
that week.
--
Sewer: Nothing to report.
b. Minutes
of the July 15, 2015 regular meeting.
D. Smith/L. Comstock all in favor to
approve the minutes of the July 15, 2015 regular meeting.
Staff noted that she inadvertently neglected
to agendize the minutes of the July 22, 2015 special meeting, so will do so on
the September meeting agenda.
c. Warrants.
L. Comstock/G. Godino all
in favor to approve the warrant
list.
d. Scheduling of Next Meeting(s):
September 16, 2015 at 7:30
p.m.
15. Adjournment.
9.49 p.m.